For the renovation of the control room of ore handling company EECV in the Europoort, Anomalie worked directly for Brand Control Rooms, the builder of the control room. We removed the old floor tiles, thoroughly cleaned the subfloor and the substructure, and laid 113 mΒ² of new calcium sulphate panels with a solid antistatic top layer of Forbo Colorex SD. The control room stayed in operation the whole time: we worked in sections around the operators and their equipment, so ore handling never had to stop. With two installers, the job was done in four days.
| Client | Brand Control Rooms |
|---|---|
| End client | EECV |
| Sector | Control Rooms |
| Floor type | Replacement of raised floor panels |
| Floor area | 113 mΒ² |
| Location | Europoort, Rotterdam |
| Period | 2026 |
| Grid | 600 x 600 mm |
| Floor panels | Calcium sulphate |
| Finish | Forbo Colorex SD solid, antistatic |
| Extras | Removal of old tiles, cleaning of subfloor and substructure, carried out during operation |
A new antistatic floor in the control room, installed in four days without the control room or ore handling coming to a standstill.