Request Quote
For Serverfarm, Anomalie supplied and installed over 650 m² of raised computer floor between 2022 and 2025 in the AMS1 datacenter on the Archangelkade in Amsterdam, using its own materials and its own installers. The floor stands at 600 mm on a steel substructure in a 1200 x 600 mm grid, with antistatic HPL panels and steel ventilation panels to cool the server racks. We also built two ramps, including a 5100 x 2870 mm ramp for heavy transport up to 4,000 kg, and repaired the existing floor and ramp. The work was carried out in phases while the datacenter remained fully operational.
| Client | Serverfarm |
|---|---|
| Sector | Datacenters |
| Floor type | Raised computer floor with ramps |
| Floor area | Over 650 m² |
| Location | Archangelkade, Amsterdam |
| Period | 2022 to 2025, in phases |
| Floor height | 600 mm finished (build height 570 mm) |
| Grid | 1200 x 600 mm |
| Floor panels | 600 x 600 x 38 mm, type 2 chipboard with steel base plate |
| Finish | HPL Abet Walkprint, antistatic |
| Ventilation | Steel ventilation panels, 38% open area, with airflow control |
| Extras | Two new ramps, modification of existing ramp, repair of existing floor |
One floor system in every hall: the same height, the same panel, the same finish. That keeps future extensions and replacements simple.